Construction

Deconstruction concept, tendering, supervision of pollutant clean-up, gutting, blasting, construction of excavation pit with special foundation engineering

Picture1_586x439-300x300

Project details

  • Deconstruction concept, tendering, supervision of pollutant clean-up, gutting, blasting, construction of excavation pit with special foundation engineering
  • 2017 - November 2018 Completion of excavation pit
  • Project developers and asset managers:
    Transaction manager, landlord, asset and property manager, project developer and builder
  • Conducted by M&P Cologne

SIMILAR PROJECTS

Picture3-1-300x300
BV Deconstruction Muskator Works Düsseldorf
Construction
Picture1-300x300
BV Deconstruction Märkisches Zentrum Berlin
Construction
error: Content is protected !!!